Northshore Update
July 2006
 
6/22 – 6/30
Begin back fill on 1st level of parking

6-26 – 6/28
Cable installation

6/28
Pour parking ramp

7/5
Start 2nd level south side

7/5 – 7/11
Pour deck area

7/14
Start framing podium level

 

 